Purchase orders › PO-26-0282

PO-26-0282 India Received

Moradabad Artisan Metalware · Sundries & Cleaning · Buyer Priya Menon
Quoted 29 Apr
Ordered 3 May
Confirmed 7 May
In production 11 May
On vessel 29 May
Customs 2 Jun
Arrived 4 Jun
Received 6 Jun

RULE Delivered and receipted.

What happened, and why

Emails on the left, the status changes they caused on the right
DateEmailStatus change / decision
29 Apr
Quoted
Recorded
3 May
Quoted → Ordered
Recorded
7 May
Ordered → Confirmed
Recorded
11 May
Confirmed → In production
Recorded
29 May
In production → On vessel
Recorded
2 Jun
On vessel → Customs
Recorded
4 Jun
Customs → Arrived
Recorded
6 Jun
Arrived → Received
Recorded

Lines

2 SKUs
SKUDescriptionOrderedReceivedUnit priceLine value
SC-002Scouring pads, 10-pack 1,300 gross 1,300 AED 42.00 AED 54,600
SC-006Tea glass set, 6 pcs 1,200 ctn 1,200 AED 54.00 AED 64,800
TotalAED 119,400

Goods receipts

GIN-26-0282 · 6 Jun 2026 Matches PO

SKUItemOrderedReceivedShort
SC-002Scouring pads, 10-pack1,3001,300—
SC-006Tea glass set, 6 pcs1,2001,200—

Key facts

ValueAED 119,400 FPOFPO-26-0282 GINGIN-26-0282 Created29 Apr 2026 ETA4 Jun 2026 +2d vs original 2 Jun VesselMV Arabian Tern Last contact— SupplierImran Siddiqui · LC at sight

Actions on this PO

Nothing waiting on anyone.