Chase supplier 5
Reorder 4
LC expiring 1
LC amendment 1
Price change 1
Customs hold 1
Availability 1
58PRIORITY
PO-26-0417: 7 days late in Confirmed — chase supplier
Stock-out in 1.9 wksAED 102k7 days late
30PRIORITY
PO-26-0418: 6 days late in Ordered — chase supplier
AED 584k6 days late
27PRIORITY
PO-26-0411: 3 days late in In production — chase supplier
AED 447k3 days late
25PRIORITY
PO-26-0406: 9 days late in In production — chase supplier
AED 177k9 days late
23PRIORITY
PO-26-0404: 5 days late in In production — chase supplier
AED 211k5 days late
Chase supplier · raised 16 Nov 2026
PO-26-0406: 9 days late in In production — chase supplier
25PRIORITY
PO-26-0406
IN
Rajkot Coolline Appliances Pvt. Ltd.
In production
AED 177k · ETA 29 Nov 2026
9 days over norm
Why this is here
RULE 21 days in In production vs norm 12; no supplier contact for 21 days
AED 177k9 days late
Suggested action
AI high confidence
Save this reply to Drafts for you to review and send from your mailbox.
Draft reply to nikhil@coolline-rk.example · written by claude-sonnet-5-5
PO-26-0406: production status and firm ship date needed by 18 Nov 2026
Dear Nikhil Patel,
PO-26-0406 has been in production for 21 days. Our normal time for this stage is 12 days. We last spoke on 26 Oct 2026.
Please send us the following by 18 Nov 2026:
1. The date production started.
2. A firm ship date.
3. Any shortfall in quantity or any other problem that may affect the order.
If the ship date has changed, please tell us the reason.
Best regards,
Sara Haddad
Demo Trading Co.✉︎ Never sent from this app. Approving saves it to your Drafts folder; you send it yourself.
✎ Edit before approving
Deciding as Sara Haddad. Your decision, the suggestion and the final values go to the audit log.