PTProcurement Control Tower
Mon 16 Nov 2026
Tekmindz theme

Action centre

What needs a decision today, most urgent first. The AI and the rules suggest; a buyer approves, edits or rejects. Every decision is logged.
All 14 Chase supplier 5 Reorder 4 LC expiring 1 LC amendment 1 Price change 1 Customs hold 1 Availability 1
Reorder · raised 16 Nov 2026

SC-005 Garbage bags, heavy duty: stock-out risk — raise PO?

33PRIORITY
SC-005 · Garbage bags, heavy duty
Why this is here
RULE cover 7.0 wks; next arrival in 9.0 wks; short 521 ctn
Stock-out in 7.0 wksAED 64k
Suggested action RULE
Raise an RFQ / new PO with Moradabad Artisan Metalware (IN-MAM):
Quantity1,100 ctn
Unit priceAED 58.00
ValueAED 63,800
Lead time30 days
Stock cover now7.0 weeks · next PO lands in 9.0 weeks
Quantity basis: Bridge the gap: 521 ctn short before the next arrival + 2 wks safety stock, rounded to MOQ 100
Supplier choice: Preferred supplier lead time 9 wks is after stock-out in 7.0 wks; alternative arrives in 4 wks
Alternatives: CN-NBK (64 days), IN-MAM (30 days)
✎ Edit before approving
Deciding as Sara Haddad. Your decision, the suggestion and the final values go to the audit log.